REALIZATIONS
STAGES OF CONSTRUCTION OF THE MAGILINE SWIMMING POOL
STAGE 1 - DAY 1-2
- measurement of the pool location
- precise excavation for the pool basin
- formwork for screed
- concreting of the so-called sub-concrete






STAGE 2 - DAY 3-4
- unloading of pool elements
- assembly and leveling
- reinforcement and concreting of the swimming pool






STAGE 3 - DAY 5-6
- pouring the bottom of the pool with the so-called mixer
- installation of pool edges
- grinding the bottom of the pool
- arranging sponge and felt







STAGE 4 - DAY 7
- liner assembly
- installation of lamps, skimmer, counter-current
- filling the pool with water








STAGE 5 - DAY 5-7
(in parallel)
-
installation of pool automation systems
-
installation of a safety cover
-
installation of a heat pump






STAGE 5 - option
- roof assembly
- construction of a beach and recreation area